Downtown Fort Worth's South End Is Getting a Courtroom Before It Gets a Steakhouse

The Fort Worth Convention Center arena, the round "flying saucer" that has shown up in aerial photos of downtown since 1968, held its last public event on September 20. The City of Fort Worth called it "It's Goin' Down," and the arena now closes for remediation and demolition in early 2027. Two months earlier, a few blocks away, the Texas A&M University System opened its first finished building on its downtown campus. Over the same stretch, at least three restaurants announced for the south end either pushed back their opening targets or haven't set one.

That order is the story of this part of downtown right now. The big institutional projects are running on published schedules and opening when they said they would. The hospitality layer that is supposed to serve them is still mostly signage and leases. If you live in Fort Worth and come downtown for dinner, events or errands, plan around the projects with dates and treat the rest as maybe.

Why the Saucer Is Coming Down

The arena sits on a circular one-story base that sticks out past its edges, which is why it looks like something that landed. The City's own history of the building says that same shape became a practical problem, because it was hard to adapt to the increasingly elaborate production needs of modern concerts and conventions.

Its replacement is the core of Phase 2 of the convention center expansion, budgeted at $606 million. Phase 1 cost $95 million and is already done, which brings the published total to $701 million. The City's February 2026 schematic design puts Phase 2 at 359,174 square feet of rentable space, including a 74,000-square-foot exhibit hall and 37,500 square feet of meeting rooms. Fort Worth Report's coverage of the plan adds a 40,000-square-foot ballroom. It also brings three more loading docks, an outdoor plaza on the north side and a tower facing Main Street.

Here's the schedule as the City laid it out in its February 2026 schematic design presentation:

  1. October 2026: abatement begins inside the arena
  2. Q1 2027: demolition of the arena starts
  3. Q4 2029: construction is complete

Visit Fort Worth's expansion page still says "early 2030." It also says the convention center stays open during construction. Either way, it's about three more years of active work on the block bounded by Houston Street, and conventions keep happening the whole time.

Phase 1 Already Changed the Street Grid

Most of the attention goes to the arena, but the first phase already redrew part of the south end. Phase 1 finished in December 2025. It added the southeast entrance, food-and-beverage facilities and four loading docks, and it straightened Commerce Street to create a pad for a future hotel.

That pad is the clearest example of the gap between infrastructure and occupants. The road work is done and the land is ready, but none of the sources we reviewed name a hotel operator or a construction schedule. For now, the hotel is a prepared site and nothing more.

The First New Building Is a Law School

The south end's newest building is Texas A&M-Fort Worth's Law & Education Building. It's eight stories and 228,000 square feet, and it opened August 5, 2026. Texas A&M Law is inside, along with other Texas A&M programs, Tarleton State programs, Texas A&M–Corpus Christi's Center for Advanced Aviation Technologies and six A&M System agencies.

For someone walking past, the most interesting feature is at street level. Fort Worth Report noted that the ground-floor windows look into classrooms, labs and a working courtroom that hosts real proceedings, including Texas Business Court hearings. The reporting doesn't promise walk-in access to the academic spaces, so think of it as something to see through the glass, not a place to tour.

The campus's next steps are spaced out and have dates attached:

  • Research & Innovation Building-A: 11 stories, broke ground the same day the law building opened, scheduled to finish in 2029
  • Performance, Visualization and Fine Arts Building: Fort Worth Report's August coverage said it could break ground seven to nine months out
  • A second research building: estimated two to four years away
  • Full five-building campus: estimated at five to seven years, depending on demand and partnerships

So RIB-A and the convention center expansion are set to finish within months of each other at the end of the decade. Through 2029, the south end will have two major construction sites running side by side.

The Restaurants Are Still a Forecast

Restaurants announced for the area are on a less predictable schedule. Here's where each one stood as of early October 2026, based on the most recent local reporting:

Project Location Latest status How the target has moved
Station & Vine 221 W. Lancaster Ave., T&P Station Own site says "Opening Fall 2026" Star-Telegram said "within weeks" in May; PaperCity said August in July
Beverly's Downtown 901 Houston St., Hogan Building basement No opening date announced PaperCity listed August in July; Fort Worth Founded's September guide says fall 2026
Al Biernat's 913 Houston St. Lease signed, early planning, no opening date Listed by a local guide as coming in 2027

Each one has a good reason to be there. Station & Vine is planned as more than a dining room: a restaurant and wine bar plus The Parlor cocktail lounge, an outdoor patio and the T&P Ballroom, and it has previewed a Sunday brunch called "The Art of Sunday" for later this fall. Fort Worth Report describes Beverly's as a planned 7,000-square-foot Mexican restaurant underground in the Hogan Building.

Al Biernat's has the best building story. The Dallas steakhouse, founded in 1998, is opening its third location in the old Farm & Home Savings building at 913 Houston, a midcentury glass-and-brick building finished in 1959. It has 11,760 square feet, floor-to-ceiling glass and a curved staircase running through the interior. The building has sat without a lasting use since the bank moved out in the 1990s, with a restaurant, retail and a hotel all considered at different times. General manager Brad Fuller, nephew of the late founder Al Biernat, confirmed the lease to Fort Worth Report in August and said no opening date has been set.

Slipping dates are normal in restaurant build-outs. The practical takeaway is simple. Book a table when a restaurant posts its hours, not when you see the announcement.

What You Can Use Right Now

Several pieces are finished and open to the public today. The T&P Passage at T&P Station is a completed public walkway connecting downtown to the train platform, with historic public art and better wayfinding. The convention center's Phase 1 entrance is open. The Houston Street and Commerce Street garages are still the main public parking, and the City lists special-event parking starting at $20 a day. The free parking the City offered in those garages for the September 20 farewell applied to that day only.

We found no published construction-related street closures or garage changes for Phase 2 this fall. The City's closure table, in a snapshot headed September 18–25, listed "various" work on Houston Street between W. 7th and W. 8th through November 20, and two-lane impacts on E. Lancaster between Main and Calhoun through October 27. Check the live City page before you drive in, since that snapshot is already a couple of weeks old.

The Fall Calendar Still Runs Through These Streets

In the meantime, the south end's busiest days this fall come from events on the same streets around the construction. Downtown Fort Worth Inc.'s street-closure listings show what to plan around:

  • Michelada Festival, October 10–11: closures on stretches of Houston, Main, Commerce, Throckmorton and cross streets, including Houston between 4th and 9th
  • Gospel Festival, November 6–7: Main Street closed between 8th and 9th
  • Veterans Day Parade, November 11: Main, Taylor, Belknap and streets between Commerce and Throckmorton from Belknap to 5th, roughly 7 a.m. to 1 p.m.
  • Turkey Trot, November 26: route streets start closing around 4 a.m. and reopen around noon
  • Tree Lighting, December 1: Main between 2nd and 5th, plus 3rd and 4th between Houston and Commerce

The Michelada Festival comes first and closes the Houston Street blocks that face both the convention center and the 900 block where Beverly's and Al Biernat's are planned. If you live downtown or regularly drive Houston Street, that's the weekend to plan around.

Hilary Waters works as a builder as well as a broker, so she watches the distance between an announcement and a finished space closely, whether it's a new arena, a restaurant build-out or a home under construction. If you're weighing a downtown Fort Worth property and want to know how construction through 2029 could affect it day to day, Virtual City Real Estate can help you separate the projects with real dates from the ones still waiting on one. Schedule a consultation.

Work With Hilary

Build with purpose. Partner with Hilary Waters to turn vision into reality through thoughtful strategy, expert construction, and real estate guidance from foundation to finish.

Follow Me on Instagram